A data center stack on two mini PCs, run by AI agents.

Where I practice the work I do for a living. Two small computers at home run the same VMware software big companies run their servers on. An AI agent does the typing. I do the cables and say go.

How it fits together

7 parts
  • over the network
  • by hand
person

Me

Plug in the USB installer, run the cables, approve any step that cannot be undone.

AI session

Claude

Plans each run with me, then splits it into parts.

AI agent

Lab runnerlab-runner

One per part. Several can run at once.

what the agent does

Types every command, reads every screen, and stops to ask me when a step leaves the plan.

network

Switch

One 2.5 Gb cable to each host.

host

Mini PC 1

  • 8 cores
  • 96 GB
  • 3 NVMe
host

Mini PC 2

  • 8 cores
  • 96 GB
  • 3 NVMe
vSAN ESAboth hosts’ disks, one pool
runs across both

VCF 5.2 management domain

  • vCenterManages both hosts and every VM.
  • NSX ManagerDraws the virtual network.
  • SDDC ManagerRuns upgrades for all of it.
in plain words

The software a company uses to run its private cloud, squeezed onto two machines.

Brought up by the agent on Oct 9

The last big run

The VCF 5.2 bring-up, Oct 9.
  • 3 h 41 min

    start to finish, with the agent at the keyboard

  • 146 of 146

    automated sub-tasks passed

  • 1 stop

    and the plan had predicted it

  • 31 runs

    on this lab since Sept 21, each one written up

How it runs

2 readers
for everyone

How it runs, in plain words.

My job is VMware. Learning it on a customer’s servers is not an option, so I keep a copy at home: two mini PCs, a switch, and the software stack I work with every day.

Setting that stack up by hand takes days of clicking through installers. Here, I plan the run with Claude, and an agent carries it out step by step while I watch.

When a step goes wrong, the agent stops and shows me the screen. Nothing that cannot be undone happens without my yes.

for builders · 1 decision

For builders

  1. One 2.5 Gb link per host.

    A cable fault splits vSAN. Accepted for a lab; the second port stays free.

Curious how any of this works?

Ask about the lab or the agents that run it. Plain answers, no jargon required.

Stack
VCF 5.2
Status
Up since Oct 9
Hardware
2 mini PCs · 1 switch
Runs so far
31 since Sept 21